ClientSite/ProjectDescription of works
Neo StructoHPCL-Mumbai·         Fabrication & Erection of Piping
·         New Treated Hexane Project·         Fabrication & Erection of Structural Steel
·         MS Maximization Project·         Equipment Erection and Alignment works
·         Dewaxing Project
·         Cooling Tower Replacement Project
Neo StructoHindalco – Dahej, GujaratFabrication and Erection of SS Converter (Consultant: Monsanto)
Neo StructoIPCL-Baroda / Turn around Job in Naphtha HeatersFabrication and Erection of –
·         Flue Gas Ducts
·         Trestle structure
·         Heater Coil works
Neo StructoPraxair/Tata-II, Jamshedpur - ASU (2x900TPD)·         Fabrication & Erection of Double wall LR Tanks (2nos.)
 ·         Erection of Cold Box and associated field works
&·         Erection & Alignment of Static & Rotary Equipments
 ·         Warm end Piping Fabrication and Erection works
Praxair/SAIL, Durgapur - ASU (700TPD)
Neo StructoTechnip/IOCL-Gujarat Refinery -·         Fabrication and Erection of Piping, Structural works
NHT/ISOM/NSU/Penex Units·         Mechanical Equipment Erection and Alignment works
PetronIOCL-Panipat Refinery / NCU ProjectFabrication & Erection of Piping, Equipment Erection works
PetronHMEL – Bathinda RefineryCDU/VDU Heater - Structural Fabrication & Erection works
Larsen & ToubroHMEL – Bathinda RefineryFabrication & Erection of Piping works in FCCU
Neo StructoTata Chemicals, Babrala unit / Turn around Project – Cap enhancement of Urea & Ammonia unitsFabrication and Erection of CS, SS and Urea grade Piping during Pre-shutdown and Shutdown
Neo StructoHPCL – Vizag Refinery / FCCU Revamp Project – Regenerator & Reactor Revamp job·         Dismantling of Ducts, Equipment, Structure, Piping
·         Fabrication and Erection of Ducts, Structure, Piping
·         Equipment erection works
Neo StructoGNFC – Bharuch, /Ammonia Synthesis ProjFabrication & Erection of Piping
Neo StructoTechnip/BPCL – Mumbai / CRU Heater Turnaround·         Dismantling of Non-pressure and Pressure Parts
·         Erection of Non-pressure and Pressure parts including hydrotesting and commissioning assistance
Cairn EnergyCairn-Mangala Processing Terminal, Barmer, RajasthanPiping fabrication and erection works. Part of jobs executed during shutdown.
Fernas /OPALOpal-Dahej / Utilities and Fire Water Spray SystemFabrication and Erection of Offsite Piping, Fire water Spray piping around Horton Spheres
Larsen & ToubroRIL-Dahej Unit / Ethane Receiving and Storage ProjectFabrication and Erection of Piping
Air LiquideBhushan Steel, Angul /Air Separation Unit - 700TPDFabrication & Erection of Piping works
Air LiquideJSPL, Angul / Air Separation Unit - 2x1250TPDComplete Mechanical, Piping and Structural steel works + Erection of Cold Box
Air LiquideAL Holding, Pune / Air Separation Unit - 210 TPDComplete Mechanical, Piping and Structural steel works + Erection of Cold Box
Tata ProjectsJSPL – Angul / Coke Oven, RMHS & Utility ProjectErection, Alignment and Welding of Building & Technological Structure
RelianceJ3-Jamnagar Project/Units: Algaetec, MEG, ROGC, PX4 & LLDPEMechanical, Piping works